( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.

AQuantitative Risk Analysis

BQualitative Risk Analysis

CEnterprise Environmental Factors

DRisk Management Plan

正确答案

答案解析

翻译:(71)利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。A.定量风险分析 B.定性风险分析 C.企业环境因素 D.风险管理计划